A TM44 report is the air conditioning inspection report that an accredited energy assessor lodges on the government register after inspecting a system with an effective rated output over 12 kW. GOV.UK says it must give the building address, the assessor's name, their employer or trading name and address, the inspection date and the accreditation scheme, carry a register reference number, and advise on the system's likely efficiency, faults, maintenance, controls, sizing against the cooling load and its ability to run efficiently, ending with a summary of the key recommendations. TM44 itself is the CIBSE technical memorandum, currently the 2012 edition, that sets out how the inspection is done. Below is each required part, then a worked sample report for a fictional office. If you want the price of an inspection, our TM44 inspection cost guide compares eight firms' published fees.

TM44 meaning: the method, the report and the register
TM44 is short for CIBSE Technical Memorandum 44, Inspection of Air Conditioning Systems. The current edition was published by CIBSE in 2012 and replaced the 2007 edition. It describes how an inspection is carried out, with a simpler procedure for packaged systems such as splits and a full procedure for centralised plant, and it is the method the government guidance points energy assessors to.
The legal duty comes from Part 4 of the Energy Performance of Buildings (England and Wales) Regulations 2012, which covers inspections, reports and the keeping of records. People say TM44 report, TM44 certificate or air conditioning inspection report. They all mean the same document: the report an accredited air conditioning energy assessor produces and lodges.
Since 6 April 2012 a report has to be lodged on the register to be valid. GOV.UK says every report must contain a valid reference number, that the number can only be generated once the report has been lodged, and that the assessor may give the owner a copy only after the report is on the register. A document with no register reference is not a valid TM44 report.
What GOV.UK says every TM44 report must contain
The government guidance lists the administrative details a report must include, and says the list is a minimum, not a limit. It then lists the advice the report will include at least. The table below sets out each required part in the order a reader usually meets it.
Some assessors add more. easyEPC, for example, says its reports include an asset register, energy calculations and site photos alongside the findings and recommendations. Those extras are useful, but the items in the table are the ones the guidance requires.
| Part of the report | What GOV.UK says it must contain | What to check when you read it |
|---|---|---|
| Building | The address of the building in which the system is located | The address matches the building and the areas served are the ones you operate |
| Assessor | The name of the accredited energy assessor | A named person, not just a company |
| Employer or trading name | The name and address of the assessor's employer, or the name and address a self-employed assessor trades under | Who to contact if the report is wrong |
| Date | The date on which the inspection occurred | The next inspection is due no more than 5 years after this |
| Accreditation scheme | The name of the government approved air conditioning accreditation scheme the assessor belongs to | The scheme you complain to if the assessor cannot help |
| Reference number | A valid reference number, generated only once the report is lodged on the register | Search it on the GOV.UK register to confirm the report is lodged |
| Efficiency | The likely efficiency of the system and any suggestions for improvement | Whether the assessor judged the plant reasonable for its age and type |
| Faults | Any faults identified during the inspection and suggested actions | Items for your maintenance contractor to price |
| Maintenance | The adequacy of equipment maintenance and any suggestions for improvement | Whether service records were seen and judged enough |
| Controls | The adequacy of the installed controls and control settings and any suggestions for improvement | Set temperatures, operating times, zones and any heating and cooling at the same time |
| Sizing | The current size of the installed system in relation to the cooling load and any suggestions for improvement | Whether plant is oversized or undersized for how the space is used now |
| Optimisation | Consideration of the capabilities of the system to optimise its performance under typical operating conditions | Whether the system could run more efficiently day to day |
| Summary | A summary of the findings and the key recommendations | The short list to act on, usually at the front or the end |
A worked sample TM44 report, section by section
This is an illustrative example of a fictional building. The building, the plant, the figures and the findings are made up to show how each required part of a report reads in practice. It is not a real report, not copied from any assessor's template, and real reports differ in layout. The headings follow the required contents in the table above.
The fictional building is a two-storey office of about 600 square metres with three air conditioning systems. Read down the right-hand column to see the kind of entry each part of a report holds.
| Report section | Sample entry (fictional) |
|---|---|
| 1. Building | Fictional two-storey office, about 600 m2, open-plan offices on both floors, one meeting room and one comms room |
| 2. Assessor, employer and scheme | Assessor's name, employer's name and address, and the name of the accreditation scheme (placeholders in this example) |
| 3. Inspection date and reference | Date of the site visit, and the register reference number issued when the report was lodged |
| 4. Systems inspected | System 1: VRF heat pump, 1 outdoor unit, 10 ceiling cassettes, 28 kW. System 2: two wall splits on one controller in the meeting room, 2 x 5 kW. System 3: one wall split in the comms room, 3.5 kW. Total recorded: 41.5 kW |
| 5. Documents seen | Installation manuals for System 1, service records for the last 2 years, no commissioning records for Systems 2 and 3 |
| 6. Likely efficiency | System 1 judged reasonable for its age. Systems 2 and 3 are older units with lower efficiency. Suggestion: plan replacement of System 2 when it next needs major repair |
| 7. Faults and suggested actions | System 1 outdoor coil partly blocked by leaves. Suggested action: clear and clean at the next service |
| 8. Maintenance | Cassette filters visibly dirty. Service visits are annual. Suggestion: clean filters more often, as the maker's manual sets out |
| 9. Controls and settings | Cassettes set to cool at 19°C while radiators heat the same open-plan zone. Time clock runs 06:00 to 22:00, seven days. Suggestions: raise the cooling setpoint, match the schedule to occupancy, stop heating and cooling running together |
| 10. Sizing against cooling load | System 2 judged oversized for a room used two days a week. System 3 judged suitable for the comms room load |
| 11. Optimisation | System 1 can be scheduled by zone from its central controller but every zone runs on one timetable. Suggestion: set zone schedules so empty areas switch off |
| 12. Summary and key recommendations | 1. Fix the setpoint and schedule clash with the heating (low cost). 2. Clean the coil and filters (maintenance). 3. Review System 2 at replacement (capital) |
How to read the recommendations
Read each recommendation as an action with an owner. Some are operational: a different cooling setpoint, a schedule that matches real occupancy, a door that should stay shut. Some are maintenance: a coil that cannot move air or filters that need cleaning more often. Some are capital: plant that is the wrong size or the wrong type. In the sample above, the cheapest recommendation, the controls clash with the heating, comes first. Real reports often follow the same pattern.
GOV.UK says there is no legal requirement to act on the recommendations. The report advises. It does not appoint a contractor or approve a budget. Recommendations you accept become a project with installation quotes. Recommendations you decline stay in the file with a reason, so the next assessor can see what changed and why.
GOV.UK also says cleaning and adjusting controls do not form part of the inspection itself. If the assessor finds a timer set wrong, the report records it and the fix is yours or your contractor's.
What to have ready before the assessor visits
The guidance says the assessor will ask the building owner or manager for a list of relevant records, for sight of the main documents before the visit, and for site records to be available on the day. It says any available documentation must be provided before the inspection, including catalogue information and details from installation, commissioning and maintenance.
Gathering these in advance shortens the visit and gives a better report. A report written without records leans on what the assessor can see, and the maintenance section will say so.
- Equipment list or asset register: make, model and rated output of each indoor and outdoor unit
- Installation and commissioning records, and the maker's manuals where you have them
- Service and maintenance records, including F-gas leak check records
- Controls information: BMS or central controller settings, time schedules and zone layout
- The previous TM44 report and its register reference number, if there is one
How it differs from a service sheet and an F-gas record
A service sheet says the filters were cleaned and the pressures were checked. A TM44 report says whether the system, as operated, is a sensible way to cool the building. Both can be true in the same month. They answer different questions. File them separately so a buyer, a landlord or Trading Standards can see which is which.
The inspection is done by an accredited air conditioning energy assessor, which is a different qualification from F-gas certification. The company that repairs a leak is not automatically the person who can sign the inspection. Keep the assessor's accreditation scheme details with the report; they are printed on it.
Who keeps the report and who asks to see it
The duty sits with the person who controls the technical operation of the system. GOV.UK says that is usually the owner, even where day-to-day operation is contracted out, and can be the occupier under a full repairing lease. That person must keep the most recent report and pass it on when control of the system changes hands. If a new operator is not given a report, the system must be inspected within 3 months of the handover.
A buyer of a commercial building, a landlord at lease end and Trading Standards can all ask for it. Trading Standards can require a copy within 7 days. Our guide to a lost TM44 report covers the penalties and what to do if the report cannot be found.
A school, a gym, a clinic or an open-plan office can pass 12 kW with several splits that feel domestic one by one. The threshold rules, including when ratings are added together, are in our guide to TM44 inspections for systems over 12 kW.
TM44 register: how to check a report
Every lodged report sits on the government register. GOV.UK's find an energy certificate service covers England, Wales and Northern Ireland and lists air conditioning inspection reports alongside EPCs. You can search by postcode, by street and town, or by the report reference number.
A register check answers three questions: does a valid report exist, is it less than 5 years old, and who produced it. If the register shows nothing for your building, our lost TM44 report guide explains the next steps.
TM44 report cost
The price of an inspection is a separate question from what the report contains. Our TM44 inspection cost guide sets out the fees eight assessor firms publish, by number of outdoor units and by kW band, with the median, the range and what the fee should include. Ask any assessor to confirm the fee covers lodgement on the register, because without it you do not have a valid report.
Which TM44 guide answers which question
This page covers the report itself. Is TM44 a legal requirement covers whether the duty applies to you. TM44 inspections for systems over 12 kW covers the threshold and how outputs add together. The TM44 inspection cost guide covers fees. The lost TM44 report guide covers finding or replacing a report. The EPBD and TM44 compliance guide puts the inspection in the wider picture of commercial building energy rules.
Frequently asked questions
What does TM44 mean?
TM44 is CIBSE Technical Memorandum 44, Inspection of Air Conditioning Systems, currently the 2012 edition. It sets out how an air conditioning energy inspection is done. A TM44 report is the inspection report an accredited energy assessor produces and lodges on the government register.
What is in a TM44 inspection report?
GOV.UK says it must give the building address, the assessor's name, their employer or trading name and address, the inspection date and the accreditation scheme, plus a register reference number. It advises on likely efficiency, faults, maintenance, controls, sizing against the cooling load and the system's ability to optimise its performance, and ends with a summary of key recommendations.
How do I check a TM44 report on the register?
Use GOV.UK's find an energy certificate service and search by postcode, street and town, or report reference number. It lists air conditioning inspection reports for England, Wales and Northern Ireland.
How much does a TM44 inspection cost?
See our TM44 inspection cost guide. It compares the fees eight assessor firms publish, by number of outdoor units and kW band, with the median and the range.
Do I have to carry out the recommendations?
No. GOV.UK says there is no legal requirement to act on the recommendations. Keep a note of what you did and did not do with the report, because the next inspection will look at what changed.
How long is a TM44 report valid?
Inspections must be no more than 5 years apart, so a report covers the system for up to 5 years from the inspection date. The first inspection is due within 5 years of the system first being put into service.
Is a service contract the same as a TM44 inspection?
No. Servicing keeps the plant working. A TM44 inspection is an energy assessor's visit with a lodged report, required at least every 5 years when the system is over 12 kW.
Can my installer write the report?
Only if they are also an accredited air conditioning energy assessor. F-gas certification is a different qualification. Ask which one they hold.
Does a house with one split need this?
A single domestic split is almost always under 12 kW. The duty is for larger systems. If several units are controlled as one system and the total may exceed 12 kW, check the legal-requirement guide before you assume you are clear.
Core buying guides
Start with these high-intent guides, then dig into the rest of the library.
Related guides
- TM44 Inspection Cost UK: 8 Assessors' Published Fees Compared (2026)
- Is TM44 a Legal Requirement in the UK?
- TM44 Air Conditioning Inspections for Systems Over 12 kW
- Lost Your TM44 Report? How to Find or Replace an Air Conditioning Inspection Report
- EPBD and TM44 Compliance for Commercial Air Conditioning in the UK
More planning guides
Sources and further reading
- GOV.UK: a guide to air conditioning inspections, required report contents, documentation, reference numbers (updated 5 November 2026, checked 28 Nov 2026)
- GOV.UK: get your air conditioning system inspected (checked 28 Nov 2026)
- GOV.UK: find an energy certificate (checked 28 Nov 2026)
- CIBSE: TM44 Inspection of Air Conditioning Systems, 2012 edition (checked 28 Nov 2026)
- legislation.gov.uk: Energy Performance of Buildings (England and Wales) Regulations 2012, Part 4 (checked 28 Nov 2026)
- easyEPC: TM44 air conditioning report, what its reports include (checked 28 Nov 2026)
- GOV.UK: certification for companies working on equipment containing F-gas
How this guide was prepared
This guide was written by the Local AC Installers Editorial Team. We compare official guidance, legislation and established consumer information, separate general information from project-specific advice, and show publication dates and sources. We do not accept installer accreditation claims at face value.